From some of the pics, can see the cement floors for the base of the blocks already. Finally.. after seeing them digging and laying the foundation for so long, we can see some real action! Sometimes when I look at the pics, I really cant see the progress, cos its all orange soil and constant drilling and digging to me.
From the forum, my future neighbours have sighted tower cranes inside the site, meaning we should be able to see them stacking up the levels 1 by 1 soon! This is really exciting news for us! I really cant wait to see more progress and hope they can complete the project faster!!
Below is the approximate timeline from bidding til now
- Feb 2009 - HDB Lauch Champions Court BTO
- 26 May 2009- Selection of unit
- Jul 2009- Payment of $2K deposit
- 5 Oct 2009- Signing of Lease agreement and payment of 5% deposit
- May 2010 - Sighting of Tower cranes !
We will continue to monitor the progress, if all goes well, hopefully we can get our flat by end of next year, after our wedding! Jia you Team Build!!!


2 comments:
so gd sia.. mine still long way to go.. :(
Hopefully ur contractor is v efficient!!I also waited until neck v long sia.. the foundation really take so long.. u see like no progress like tat one..